List of water supply and sewer facilities requiring investments for their construction
No. p / p |
Object name |
Availability of design and estimate documentation |
Estimated cost, euro |
Justification of construction |
Объекты водоснабжения |
||||
1 |
Off-site networks and facilities in the city of Berezino, Minsk region |
expert opinion dated February 22, 2011 No. 1730-15/10
|
3 200 000 |
The urban population is 11.9 thousand inhabitants. The main source of water supply is 11 single wells. The coverage of the population with centralized water supply is 11.7 thousand people. (98%). The average concentration of iron in the water supply system is 1 mg/l. In the summer period - long-term interruptions in water supply. |
2 |
Construction of a water deironing station in Zaslavl |
need to develop |
1 500 000 |
Most of the city is supplied with water from the water intake "Khmelevka" (5 art wells), with a capacity of 3150 m³ / day. The population is 14.3 thousand people. The average concentration of iron in the water supply system is 1.0 mg/l. |
Water disposal facilities |
||||
3 |
Reconstruction of the sewerage system in the city of Fanipol (including the construction of new sewage treatment facilities) |
The design and estimate documentation has been developed and is being reviewed |
5 000 000 |
The existing sewage treatment facilities have been operated without modernization for more than 45 years, the wear of structures and equipment is 90%. |
4 |
Очистные сооружения канализации г. Любани
|
conclusion of the examination dated 06.05.2011 No. 292-15/11 |
9 990 000 |
Wastewater treatment plant in Lyuban |
5 |
Sewerage of the city of Uzdy (including the construction of treatment facilities) |
expert opinion dated September 27, 2012 No. 651-15/12 |
6 800 000 |
The equipment for biological wastewater treatment is not functioning, the wear of structures is 80%. The project provides for the reconstruction of sewer collectors, pumping stations and treatment facilities. |
List of boiler facilities requiring investments for their reconstruction
No. p/p |
Business name | Boiler room / facility | Address | Installed boiler equipment | Type of fuel | Installed capacity, Gcal/h | Attached load, Gcal/h | Year of construction | Estimated cost, million rubles | Implemented power, MW | ||||||
General | MW | Gas | liquid | General | Heating | DHW | Steam, vent. |
|||||||||
1 | Municipal unitary enterprise "Kopyl housing and communal services" | Boiler room No. 1 | Kopyl, st. Thermal, 1 | DKVR-6.5/13GM (2 pieces), DE-25-14GM (1 piece) | gas | 23,751 | 23,751 | 10,998 | 7,498 | 3,500 | 1977 | 6,5 | 8,0 | |||
2 | Republican unitary enterprise "Lubansk housing and communal services" | Central boiler house Luban |
Luban, per. Socialist, 1 | DE-25-14GM (1 pc.), DE-25-10GM (1 pc.), DKVR-10/13 (1 pc.) | gas | 38,000 | 38,000 | 15,940 | 14,190 | 1,750 | 1977 | 7,0 | 10,0 | |||
3 | UE "Myadelskoe housing and communal services" | Boiler room Myadel |
Myadel, st. Industrial | KVGM-20 (1 pc.), KVGM-10 (1 pc.), DKVR-10/13 (2 pcs.), E-1/9 (2 pcs.), Tendom QantoC1200 (1 pc.) | gas | 45,072 | 36,472 | 8,600 | 37,625 | 28,790 | 6,454 | 2,381 | 1971 | 10,0 | 16,0 | |
4 | UE "Zhilteploservis" KH Pukhovichsky district | Boiler room No. 1 | Maryina Gorka, st. Andreevskaya, 2 | PTVM-30 (2 pcs.) | gas | 60,000 | 60,000 | 24,980 | 17,900 | 7,080 | 1986 | 9,0 | 15,0 | |||
5 | Municipal unitary enterprise "Slutsk housing and communal services" | Boiler room #2 |
Slutsk, st. 14 Partizan, 100 | DKVR-4/13 (2 pcs.), KVGM-30 (2 pcs.) | gas | 65,200 | 65,200 | 29,500 | 19,860 | 9,640 | 1986 | 10,0 | 16,0 |